Field composites
Anand 49 years · Project-finance head · ReNew / Tata Power Renewables / Adani Green / Avaada comparable
Anand's firm won a 400 MW solar auction issued by SECI at ₹2.42/kWh — a headline tariff that was celebrated in the press release. The project-finance committee sees a different number: the tariff envelope at which the lender will reach financial closure. The PPA is unsigned. The Letter of Award is 11 months old. The land-acquisition file is 60% complete. At the current tariff, with module cost, BoS, and interconnect capex at Q3 2026 spot prices, the levelised-cost gross-to-net gap requires the developer to carry a 14–18% capital cushion on the balance sheet until PPA execution.
The lender's credit committee does not lend against an auction win. It lends against a signed PPA with an offtake-creditworthy counterpart. The counterpart — the state DISCOM — has not signed. Its board resolution window expires in six weeks. The project's IRR on a fully-amortised 25-year basis holds at the auction tariff only if COD is achieved within 24 months of PPA execution. Every month of pre-PPA delay is a silent equity erosion that the quarterly segment filing does not surface.
Priya 38 years · Procurement officer · state electricity distribution company
Priya's DISCOM is the designated offtake counterpart for three SECI-issued auctions totalling 1,100 MW. She has not signed any of the three PPAs. The constraint is not political — it is structural. The DISCOM's avoidable-cost benchmark, set by the state regulator, is ₹2.28/kWh for the current procurement cycle. Two of the three auction tariffs cleared ₹2.40–₹2.48/kWh. The board cannot sign a PPA at a tariff above avoidable cost without a regulatory order permitting the deviation — and that order has not arrived.
The third auction at ₹2.21/kWh clears the benchmark. Its PPA is in legal review, but the DISCOM's transmission-corridor capacity for that project's injection point is oversubscribed until FY28. Signing the PPA without a transmission-availability letter exposes the DISCOM to curtailment liability. The composite scenario surfaces a state where three projects are auction-complete and none are PPA-signed — not because the tariff is wrong, but because the regulatory and infrastructure sequencing has not caught up to the auction calendar.
Vikram 52 years · Senior policy officer · Ministry of New and Renewable Energy
Vikram's division has issued FDRE (Firm-Dispatchable Renewable Energy) and BESS-bundled auction formats to address the must-run curtailment risk that made earlier tariffs unsignable for DISCOMs. The auction product mix has evolved: from flat-solar PPA to hybrid (wind+solar) to FDRE (with intra-day dispatchability guarantee) to FDRE+BESS (with 4-hour storage). Each format adds complexity to the contract and capex to the developer's model.
- FDRE format requires the developer to guarantee a scheduled generation shape. The BESS LCOS at current cell prices adds ₹0.55–₹0.85/kWh to the levelised tariff. The auction-discovery tariff does not always absorb this — winners have bid below their own LCOS floor in competitive pressure.
- Must-run / curtailment risk allocation in SECI-issued PPAs differs from state-DISCOM-issued contracts. State PPAs often do not guarantee compensation for grid-instructed curtailment. The developer's IRR model, built on the SECI template, does not match the state template the DISCOM wants to sign.
- The DISCOM-friendly contract design Vikram's division is now piloting includes a two-part tariff (capacity + energy), a curtailment-payment clause, and a transmission-availability condition precedent. Pilot term sheets have been issued to three states. None have been executed. The design is the right answer. The execution pipeline is not moving at the pace the 500 GW-by-2030 target requires.